articles | 08 August 2017

Floating gas terminal could be ideal for Cyprus

Given the prospect of new gas discoveries in Cyprus’ EEZ, it is timely to review recent developments, says Charles Ellinas, energy expert.

Floating liquefied natural gas (FLNG) scored some notable successes so far in 2017, to the extent that the world may be witnessing a resurgence of this technology. The attainment of a number of successful milestones over the last few months is bringing interest back. In fact, 2017 is turning out to be a big year for FLNG.

Key FLNG milestones

By 2018, there will be three operating FLNG projects: Petronas’ PFLNG Satu, Perenco’s FLNG Hilli and Shell’s Prelude.

The world’s first FLNG vessel, known as PFLNG Satu, with a total LNG processing capacity of 1.2 million-tonnes-per-annum (mtpa) and an estimated cost of $1.6bn, positioned at the Kanowit gas-field off Sarawak is now operational. Petronas’ Satu project came on stream and started producing LNG early December and exported its first LNG early April.

Emboldened with this success, Petronas is proceeding with the construction of its second FLNG vessel, PFLNG-2, announcing in May that will be operational by 2020. It will be deployed at the Rotan field, 240km off Sabah in Malaysia, with a total LNG processing capacity of 1.5mtpa.

The second FLNG vessel to become operational, with 1.2mtpa LNG capacity, will be for the Kribi gas-field offshore Cameroon, operated by Perenco and Cameroon’s SNH.

Golar is supplying the unit, known as FLNG Hilli Episeyo. It is also the first LNG carrier to be converted into an FLNG unit. It is aiming to start production in September.

Golar plans to follow this up with the Fortuna FLNG vessel to be installed in Ophir Energy’s block-R, about 100km offshore Equatorial Guinea. Fortuna’s LNG capacity will be 2.5mtpa and it is scheduled to become operational in 2020. FID is expected in August.

The next milestone will be Shell’s Prelude FLNG. After sailing 5,550km from Korea, it is now at location at the Prelude gas-field, 475km offshore Western Australia, where it will stay for 25 years. At 600,000 tonnes it is the biggest floating structure ever constructed, with staggering dimensions of 488m by 74m, at a total cost of about $12.6bn. It will be producing 3.6mtpa LNG and it is expected to start operating in 2018. It should be noted that this cost includes facilities to produce 5.3mtpa liquids, 1.3mtpa condensate and 0.4mtpa LPG. It is a prototype that the industry is watching with great interest.

Another important milestone is Eni’s FID for Coral FLNG, in Mozambique, taken in June. The importance of this lies in the fact that FID has been taken in a low price environment, a strong indication that the FLNG concept can be viable even at low prices.

Coral FLNG will have an LNG capacity of 3.4mtpa. In October 2016, Eni and its Area 4 partners signed an agreement with BP for the sale of the entire volumes of LNG produced by the project for a period of over 20 years. These partners will, once cleared, include ExxonMobil, which bought 50% of Eni’s share in March.

Where Coral FLNG is a first, is the water-depth. It will operate in 2,000m, making it the first ever ultra-deep-water FLNG. By comparison, Shell’s Prelude FLNG will be in a water-depth of about 250m. Start-up is expected mid-2022, with about 5tcf gas to be produced over 20 years.

This has great similarities to Aphrodite gas-field in Cyprus EEZ and, if drilling is successful, to potential gas-fields in Total’s Block 11. As result, development of Coral FLNG is of great importance to Cyprus’ aspirations to export its gas.

Not many LNG projects have reached FID during the last two years, reflecting the oversupply of LNG in the market. But the two projects sanctioned this year, Coral and Fortuna, are both FLNG projects. According to Wood McKenzie this highlights a positive shift in industry perception toward FLNG. Majors like Eni, ExxonMobil and BP have all now endorsed FLNG in a low LNG price environment. With stranded gas resources suited to FLNG elsewhere in the world, FLNG appears to be regaining support, especially where through standardisation construction costs are minimised.

Studies into offshore FPSOs started in the early 1970s, but it was only in the mid-1990s that significant research, backed by experimental development, began. This led to the first FPSO, Shell’s Castellon, built in Spain in 1977. Today, over 270 vessels are deployed worldwide as oil FPSOs.

Similarly, studies into offshore floating LNG started in the 1970s and by 1997 Mobil proposed the first FLNG concept, with first export from an FLNG vessel achieved this year. Indications are that FLNGs are on the way to follow a similar growth pattern. After all, FLNG is an evolution of the FPSO concept.

FLNG has now become an attractive option to develop offshore and often stranded gas-fields, holding between 2-10tcf of gas, especially for those located at significant distances from land. In comparison to onshore liquefaction, which requires an offshore production platform, a pipeline to transport the gas and an onshore LNG plant, FLNG in effect combines all of these in a single unit. This brings advantages of shorter project completion times and lower costs.

In comparison to onshore plants, which typically take 4-5 years to construct and are far more prone to delays influenced by factors such as weather, approvals, lack of infrastructure and cost overruns, the delivery track record for FLNG vessels is generally good.

Key factors driving adoption of FLNG include technological advancement, monetisation of stranded gas reserves, rising costs for the development of onshore terminals, shorter lead times, relocation flexibility, and lower space requirements.

The future of FLNG

The future of FLNG is decidedly looking better. With PFLNG Satu, and soon FLNG Hilli and Prelude, valuable operational experience is being gained giving operators, financiers and insurers more confidence in FLNG making future adoption easier.

Global capex on floating liquefaction units will total $41.6bn over the period of 2016-2022. FLNGs account for about 60% of this expenditure – the rest is for import and regasification terminals.

About half of this capex is for projects in Africa. In the longer-term, gas discoveries in remote regions offshore Africa and elsewhere will continue to drive adoption of FLNG solutions.

Shell’s Chief financial officer Simon Henry said in 2016 that FLNG is an attractive way to develop remote fields and he still expects Shell’s portfolio eventually to include several such projects.”If I look in 10-15 years time I would hope that we would see multiple FLNG projects in the Shell portfolio, because it’s a great wayof monetising gas in a competitive manner…”

The rising cost of onshore LNG terminals and the shorter lead times of FLNGs make them viable even in the current low-price market environment, as the new projects in Africa are demonstrating. This is what makes FLNG a potentially attractive option for developing and exporting Cyprus’ potential gas finds in a competitive global gas environment.

Source: Cyprus Mail

Cooperation Partners
  • Logo for Love Cyprus Deputy Ministry of Tourism
  • Logo for Association of Cyprus Banks
  • Logo for CYFA Cyprus
  • Logo for Cyprus Shipping Chamber
  • Logo for Ministry of Energy, Commerce, Industry and Tourism
  • Logo for Cyprus Chamber of Commerce and Industry
  • Logo for Cyprus International Businesses Association
  • Logo for Invest Cyprus
  • Logo for Cyprus Investment Funds Association